Livingston Park, and how this page climbs
LIVINGSTON PARK LTD raises new domestic houses, and extensions that need a warrant of their own, in Edinburgh and the councils around it.
Everything below is one house going up, in the order it happens: down to formation, up through structure, then indoors. Enquiries reach the office at works@livingstonpark.live.
What has to be in place before the dig
A warrant is granted before work begins, and the drawings issued with it govern everything after. We read them against the plot: levels, boundaries, existing drainage, where the house sits. Where drawing and ground disagree the question goes back to the designer, as a warrant amendment, before a spade goes in.
- The approved plansSite plan, floor plans, elevations and sections, each stamped and carrying a revision letter.
- Structural calculationsFoundation sizes, lintels, joist spans and the roof design, read alongside the drawings.
- The written specificationMaterials, build-ups and workmanship clauses — details no plan can show.
- The energy assessmentInsulation values and airtightness, built into the fabric as it goes up.
What a Scottish warrant settles is on the warrant page.
The first line on the ground
Setting out starts from the boundary and the site datum. A temporary bench mark goes on something that will not move, and every level is taken from it. Profiles stand clear of the dig, ranging lines run between them, corners squared by diagonal.
Plant moves pegs, so the setting out is re-checked once tracked machines have been on the ground. Nothing is poured until the offsets read the same twice.
Down to formation: what the ground gives
Topsoil comes off and is stacked on its own. Excavation follows the trench lines to the depth the ground gives, which is not always the depth drawn, and building standards see the trench open before concrete is placed.
| Found in the trench | What it changes | Who settles it |
|---|---|---|
| A soft spot | The dig carries on past the drawn depth until firm formation is reached under it. | The engineer, on site |
| Made ground | The foundation is re-designed for what is there, not deepened on the day. | The engineer, by amendment |
| An old field drain | The run is re-routed or picked up, and its position goes in the completion file. | Us, with building standards told |
| Tree roots | The foundation moves away from the tree, or goes deeper to the engineer's detail. | The engineer, on site |
| Rock | A shallower dig, different plant, a formation cleaned off rather than trimmed. | Us, on the day |
Foundations are poured against firm, undisturbed formation; blockwork then rises to damp-proof course. More on trial holes is on the ground page.
Everything that must pass under the slab
Foul and surface water stay separate from the first length of pipe to the last. Runs are set out backwards from the connection, so the invert at the house follows the fall we actually have.
Pipes are bedded in granular material and no trench is backfilled until its run has been tested. Chambers go in at every junction and change of direction, so the system can be rodded later.
Up from the damp-proof course
Above damp-proof course the shell rises in the order the loads travel. Ties, cavity trays, closers and lintels are set as the courses go up, because none can be threaded in afterwards. Joists are hung, strutted and decked; the roof is then braced, felted, battened and covered.
The day the weather stops mattering
Wind-and-watertight is a narrow milestone, and the programme hangs on it: once the building is closed the structure starts drying, and the sequence indoors becomes ours to control.
| Closed to the weather | Roof covering on, windows and external doors fitted, the building shut. |
|---|---|
| Still outstanding | Verges, rainwater goods, harling and external works, each with its own run after the date. |
| What it releases | Internal trades start, and first fix runs alongside the drying out. |
Every level is a subtraction from the datum
We work down from finished floor level through each layer to formation; the difference is the depth of the dig. Change a thickness and the levels beneath it move, here and in the section at the head of the page.
- Floor finish
- Screed
- Slab
- Insulation
- Sand blinding
- Sub-base
- Formation level
- Depth below finished floor
The figures are the ones you typed, subtracted in order. The depth actually dug is settled by the trial hole and the engineer's foundation detail.
The order the rise runs in
A house is built in one order, and most of its joints are not negotiable. Pick a stage and the list marks what finishes first, what runs alongside, and what waits. No duration is attached: that belongs to one plot.
- 01Setting out and profilesBoundary and datum fixed before any peg goes in.
- 02Excavation to formationNot until the setting out is re-checked after tracked plant.
- 03Foundations pouredNot until building standards have seen the trench open.
- 04Substructure to damp-proof courseAs soon as the concrete has gone off and the trench is signed away.
- 05Drainage runs and the connectionSet out backwards from the connection, and tested before backfill.
- 06Oversite build-up and slabNot until everything under the slab is in and tested.
- 07External walls and floor joistsAs soon as the damp-proof course is in and the oversite closed.
- 08Roof carcass and coveringNot until the walls are up and the scaffold lift checked.
- 09Windows and external doorsAs soon as the openings are formed and the lintels bedded.
- 10First fix and plasterNot until the building is wind-and-watertight and the deck dry.
- 11Second fix and decorationNot until the plaster has dried in its own time.
- 12Snagging and handoverAs soon as inspections, drainage tests and certification are in hand.
The two overlaps that really happen
Drainage goes in while substructure blockwork rises — both are below ground and the same dig serves them. Windows go in while the roof is covered, because the openings are formed and the scaffold is up.
On a live plot the order is settled by the warrant conditions, the ground, and the trades free that week. The same run is in prose on the order of work page.
Buried, closed over, then finished
Indoors the work splits in two around the plaster. First fix is everything buried before the walls close over it; second fix begins once those walls are dry. Forcing the heating before the plaster has dried opens cracks that are then made good twice, so it waits.
| First fix | Second fix | |
|---|---|---|
| Goes in | Soil stacks, services, heating pipework and the electrical carcass, against the drawing. | Doors hung, skirtings scribed, sanitaryware, radiators and the consumer unit tested. |
| Agreed first | Notches and holes through joists, cut where permitted and nowhere else. | Worktops templated once the units are level and fixed down. |
| Closes it | Insulation between and over, vapour layer lapped and taped, plasterboard, then skim. | Decoration follows the joiner; the last coat waits for every trade that could mark it. |
| Runs outside | Scaffold struck once the work above it is done. | Harling, paths and driveway, while the inside is decorated. |
Inspections, and what each one releases
Building standards inspections run right through a job, and the completion certificate depends on each being made at the proper stage.
| Trench open | Releases the foundation pour. |
|---|---|
| Drainage tested | Releases backfill, and then the oversite over it. |
| Final inspection | Booked once drainage tests, certification and commissioning are in hand. |
| Handover | Keys, warranties, the operating and maintenance information and as-built drawings, together. |
Snagging is walked with the client, written into one list, and worked through in a single pass. Anything appearing later falls under the defects arrangement in the contract.
Getting in touch
Write to works@livingstonpark.live — read at the office, where the drawings and the paperwork are kept, and the way in for a plot, a granted warrant, or an extension still being thought about. Use the office for anything on paper and the site number for anything happening today.